Indoor pool building design: a five-minute guide for architects
A practical coordination guideCoordinate the pool shell, structure, air handling and plant room before the layout is fixed.
A successful indoor pool begins with the building, pool and services being designed together. Our five-minute film explains the decisions to coordinate while the layout is still easy to change, using completed Compass project photography and an illustrative pool-hall model.
Use the checklist below when developing your concept and coordinating the design team.
Start with a box within a box
The main contractor builds the engineered structural enclosure. The pool builder installs the waterproof pool shell. The interfaces between them need agreement: support, insulation, levels, waterproofing and service connections.
The teaching model shows a continuous raft beneath the pool hall and plant room. Its beam-and-block surround has independent support and a service void below; the pool shell does not carry the surrounding floor. The structural solution must follow the engineer’s project-specific design.
Agree the shell’s delivery and installation route before closing the enclosure. Resolve ground conditions, groundwater and external waterproofing with the design team, and coordinate the pool edge, surrounding floor and thresholds from a common set of levels.
Reserve the air-handling routes from the outset
Air handling is an early architectural decision. Allow for the AHU, the complete supply and extract routes, insulation, bends, supports and access.
A useful initial duct allowance is 600 × 600 mm, or an equivalent cross-sectional area. Actual ducts can be larger and must be sized by the specialist. In the film, a flatter 1,200 × 300 mm duct sits within a dropped bulkhead. Both examples provide 0.36 m² of airway, but equal area does not mean equal pressure loss or noise.
The alternative puts the main ducts through the undercroft. This needs a usable service void, practical entry and maintenance access. Compare both routes before fixing the ceiling and floor construction.
With overhead supply, window heads typically align with the bulkhead soffit and outlets direct air down the room side of the glass. An undercroft arrangement can supply air upwards from floor outlets beside the glazing. Coordinate the distribution with the specialist, rather than treating the outlets as a late addition.
Rooflight ducts and outlets should sit beside the openings, clear of the glass. Consider glazing, solar gain, rooflight detailing and air distribution together. Include the intended pool cover in the environmental brief.
Give the plant room enough space to work
For a domestic pool, a clear 3 × 3 m plant room is a typical starting allowance, including the AHU. Locate it beside the pool hall, on an external wall for fresh-air and exhaust connections, with a door into the hall.
The final room size follows the selected equipment. Check service clearances around the AHU, filter, pumps and controls, and demonstrate how components can be removed and replaced. A door matching a unit’s nominal width does not prove that the unit can pass through it: handling space and tolerances matter too. Agree chemical storage separately.
Coordinate coping, falls and drainage
Detail the coping, shell lip, adhesive, packing and flexible joint together. The Compass section used in the film shows 300 mm overall coping width with a rounded inner edge; other profile dimensions in the teaching model are illustrative.
Form the pool surround with falls to its agreed collection point. The film shows an optional flush channel beside the coping. Use a formed screed to create the required falls: no liquid screed. Coordinate thresholds and plant-room drainage at the same stage.
Distinguish the routes for backwash, AHU condensate, floor drainage and any overflow. Confirm the duty and destination of each.
Specify the complete pool-hall envelope
Choose finishes and fixings for wet use and the actual pool-hall exposure, considering slip resistance, cleaning and corrosion. Suitability outdoors or in high humidity is a useful first question, but is not a complete specification.
Cold-bridge detailing matters at walls, roof edges, glazing and rooflights. Keep insulation continuous, coordinate the primary vapour-control layer, and seal service penetrations and junctions.
A stretch ceiling is a tensioned membrane held in perimeter tracks. A suitable system offers a moisture-resistant finish and conceals the service space. Acoustic benefits require an acoustic system to be specified. Plan access with the supplier and do not assume the ceiling alone provides the building’s vapour control.
Bring the team together before fixing the design
- Agree the brief, water temperature, pool size and cover.
- Define the structural enclosure, waterproof shell and responsibility for their interfaces.
- Reserve installation, servicing and replacement routes.
- Coordinate the AHU, ducts, glazing and rooflights.
- Confirm plant-room space using the selected equipment.
- Resolve coping levels, falls, thresholds and drainage.
- Detail materials, insulation, cold bridges and vapour control together.
- Agree heating, water, power and control interfaces, then plan commissioning and owner handover.
Bring Compass into the design before fixing the structure, ceiling and services. Contact the team to discuss your indoor pool project.
The film uses an illustrative teaching layout and AI-generated narration. It is a coordination guide, not a project-specific structural, building-envelope or mechanical design.